Project Plan¶
Ontomatica will deliver a prototype label application within 60 days of contract start date.
Ontomatica will deliver complete system within 120 days of finalizing a modified specification.
Ontomatica anticipates USDA Label Project will be open-for-business on or about May 26, 2015.
Release 0 is contract signing and start date.
Release 1 is Prototype. Prototype will reuse and modify existing Ontomatica capabilities. For example, deposition services and REST services will not be available for Release 1.
Release 2 is modified specification jointly developed by USDA and Ontomatica.
Release 3 delivers complete system. Release 3 trains USDA level 1 support on use, management and implementation of complete system.